Gamesa will supply 14 G114-2.1MW turbines to the Big Turtle site owned by the local developer. Gamesa will service the turbines for 12 years.
Delivery is expected in August 2016, with commissioning due in October.
The 14 turbines form the second phase of the project. Gamesa powered the first phase with ten G114-2MW turbines in 2014. Overall, Big Turtle will have a 49.4MW operating capacity.
The order for the first phase was Gamesa's first for the model in the US.
Gamesa claimed to have received orders of over 600MW for the G114 model – in both 2MW and 2.1MW forms – in the US.