The latest project updates
CANADA: Boralex has confirmed that construction is ongoing at the 200MW Apuiat project in Québec, in which it has a 50% stake, with commissioning scheduled for summer 2025.
GERMANY: Vestas will supply eight V150-6.0 MW turbines to ABO Energy, for the 48MWÂ Schierenberg project in Brandenburg. Delivery and commissioning are planned for 2026, after which Vestas will also provide service for 20 years.
TAIWAN: Synera Renewable Energy has acquired an additional 26% stake in the 376MW Formosa 2 offshore wind farm, raising its stake to 51%.
|