The project in听Dumfries & Galloway will feature 14 V112-3.45 MW turbines in 3.6MW power optimised mode.
The contract for 86.4MW Sandy Knowe , includes supply, installation and commissioning of the wind turbines alongside a 20-year service agreement.
Turbine deliveries are expected in Q3 2021, with commissioning due in Q4 next year.
Juan Furones, Vestas sales vice president, said: 鈥淟everaging the versatility of the 4MW platform technology combined with a long-term service agreement, we ensure maximum value for our customer鈥檚 business case.鈥