Offshore Project Progress - 3 June

EUROPE: Recent project updates from Denmark's 600MW Kriegers Flak site, the Finnish Tahkoluoto development and two sites in UK waters.

Foundation installation at Dudgeon has reached the half-way point

Krigers Flak

Substation supplier: Hollandia Offshore and Energinet.dk have signed a deal for the engineering, procurement and commissioning of the 600MW Kriegers Flak’s substations.

The scope of works includes transportation to the Baltic Sea project site. The two substations are due for delivery in April 2018. 31-May

 

Tahkoluoto

Dredging date: Jan De Nul is about to begin dredging work at the site of Suomen Hyotytuuli Oy’s Tahkoluoto project.

The 40MW development will aim to demonstrate solutions for turbines and foundations, suitable for icy conditions in the Baltic Sea. 31-May

 

Burbo Bank Extension

Topside loadout: Engie Fabricom and Iemants have completed the loadout of Burbo Bank Extension’s substation topside, at Engie Fabricom’s yard in Antwerp, the Netherlands.

The substation and jacket will be installed at the Irish Sea project site, where they will serve DONG Energy’s 258MW development. 31-May 

 

Dudgeon

Halfway installed: Half of Dudgeon’s 67 foundations have been installed, with installation progressing at the rate of three a week from the Oleg Strashnov installation vessel.

Due for completion in 2017, the 402MW project is under construction in the North Sea off Norfolk. 3-June

 

From WPO Intelligence